Tender Notice North Macedonia Wind Industry
Engineering and Construction, Windpark Project Bogdanci - Balance of Plant
Tender Award
Jul 11, 2025
- Country North Macedonia
- Financing KfW Entwicklungsbank
- Reference Number BMZ 201366889/KFW505913
- Subject Project "Windpark Bogdanci - Phase II"
Project Measures:
The Project concerns the extension of the existing wind farm Bogdanci with an expected additional capacity of 13.2-15 MW.
Tender 2: Balance of plant
- Internal cable network (MV network and fiber optic cables)
- Connection to the existing Bogdanci substation
- Internal roads
- Civil works for crane platforms and temporary storage areas
Brief Description of the Contract:
General project mangement;
- Design and engineering (necessary changes to design for building permit, the execution design and the as-built design)
- Procurement of necessary equipment and machinery
- Permitting procedure
- Providing all necessary standard and application programs (software)
- Validating the load-bearing capacity (if necessary) of the designed internal roads, if necessary, other areas necessary to build all wind turbines
- Any other tests necessary for the construction of internal roads
- Insurance, transport
- Site infrastructure
- Commissioning
- Operational acceptance
- Support and contractual obligations related to defects removal within the guarantee period
- Documentation