Hit: 280
  • Jan 30, 2020 Tender Notice Kosovo Heating
    store page page bookmarkeddownload

    Supply and installation of DH pipes

    Cancellation Notice KfW

    Financing: KfW Entwicklungsbank

    Project objective:
    Contribution to a cost-efficient modernization and expansion of the existing DH network in Pristina
    Scope of supply:
    Construction & installation of new DH pipes to new DH substations
    Replacement of existing old pipes with new DH pipes (can either be main distribution pipes or branch pipes to rehabilitated new DH substations)


    Cancellation Notice:
    All Applicants were not substantially compliant with the Qualification requirements of the Pre-Qualification Documents

  • Dec 16, 2019 Tender Notice India Water Supply, Irrigation
    store page page bookmarkeddownload

    Consulting Services, Watershed Management

    Tender Award

    Financing: KfW Entwicklungsbank

    Brief discription of the contract awarded:
    Project Objective: The main aim of the Project is to improve ensure water availability and security by mainstreaming scientific participatory approaches to sustainable catchment protection and community forest management.
    Short description: Qualified, independent consultant companies are invited to submit prequalification documents for consulting services for the implementation of the above mentioned Project. The main consulting services to be provided...

  • Dec 03, 2019 Tender Notice Jordan
    store page page bookmarkeddownload

    Rehabilitation and Upgrading of Wastewater Treatment Plants

    Cancellation Notice KfW

    Financing: KfW Entwicklungsbank

    Ref: 27/2019/SW - BMZ201166594/KFW503392
    Project: Nexus and Resource Protection - Climate Change Mitigation Measures Phase 2
    Requested services: Rehabilitation, Upgrading and Operation of Irbid Central and Wadi Arab Wastewater Treatment Plants

  • Nov 25, 2019 Tender Notice Albania Water Supply, Irrigation
    store page page bookmarkeddownload

    Consulting Services, Water Supply and Sewerage Systems

    Tender Award

    Financing: KfW Entwicklungsbank

    Brief description of the contract:
    The Project Executing Agency (PEA) is seeking to engage a qualified consultant to perform the following services for the implementation of the rehabilitation and extension of water supply and sewerage systems including wastewater treatment plants in the region of Himara and Orikum in the south west of Albania:
    • Overall management of the project
    • Detailed design incl. ESIA, tendering
    • Construction supervision
    • Assistance to the PEA during Defects Notification...

  • Nov 20, 2019 Tender Notice Bangladesh
    store page page bookmarkeddownload

    Consulting Services, Climate Resilient Infrastructure

    Cancellation Notice KfW

    Financing: KfW Entwicklungsbank

    Climate Resilient Infrastructure Mainstreaming (CRIM) Project incorporating the Climate Change-Adapted Urban Development Programme (CCAUD) - Satkhira Component Phase I
    Ref. No.: FP 0004, 2014 67 984/2150 10 293
    Project measures/Objective:
    The purpose of the Project is to integrate climate change adaptation systematically into decision-making for infrastructure planning, supervision and maintenance of the Local Government Engineering Department (LGED).
    The Consultant shall provide Consulting...

  • Nov 18, 2019
    store page page bookmarked
  • Nov 18, 2019
    store page page bookmarked
  • Nov 18, 2019
    store page page bookmarked
  • Nov 18, 2019
    store page page bookmarked
  • Oct 31, 2019 Tender Notice Bangladesh
    store page page bookmarkeddownload

    Consulting Services, Climate Change Adaption of Urban Infrastructure

    Tender Award

    Financing: KfW Entwicklungsbank

    Brief description of the contract:
    The Services requested are for a Feasibility Study, which, among others, (i) reviews and reality-checks existing urban development plans and data, (ii) carries out a Climate Risk Assessment analysis of the Project Area, (iii) identifies a wide range of suitable climate adaption measures / interventions, and, (iv) following a more detailed analysis and prioritisation, (v) further studies and prepares prioritized climate adaptation measures to feasibility level for...