Tender Notice North Macedonia Wind Industry

Engineering and Construction, Windpark Project Bogdanci - Wind Turbines

Tender Award

  • Country North Macedonia
  • Financing KfW Entwicklungsbank
  • Reference Number BMZ201366889/KfW505141
  • Subject Project "Windpark Bogdanci - Phase II"

Project Measures:

The project concerns the extension of the existing windpark Bogdanci I with an expected additional capacity of 13.2-15 MW  (EPC project)

Tender 1: Wind Turbines

• Delivery and installation of 3 or 4 wind turbines

• Delivery and installation of wind turbine foundations

• Long-term service agreement and availability and power curve guarantee

 

Brief Description of the Contract:

• General project management;

• Design and engineering (necessary changes to design for building permit, the execution design and the as-built design);

• Procurement of necessary equipment;

• Insurance and transport of equipment;

• Factory testing of equipment; • Equipment testing after delivery;

• Erection and installation of the procured equipment;

• Trial operation of all individual power plant systems to determine their joint functioning as part of a whole;

• Site infrastructure;

• Installation and commissioning;

• Guarantee tests, including power curve validation

etc.